The State Energy Supervision Inspection of Ukraine has summarized the readiness of distribution system operators to ensure the stable operation of the electric grid during the autumn-winter period of 2025/2026.
This is reported by Finway
Execution of Preparation Plans and Addressing Deficiencies
According to the approved schedules, operators were to implement 4,858 measures for this season, of which 4,288 were identified as primary and 570 as additional. Currently, according to the State Energy Supervision, about 82% of the necessary work for the reliable functioning of energy facilities during the increased winter loads has been completed.
“According to the preparation plans, distribution system operators were to implement 4,858 measures, of which 4,288 are primary and 570 are additional. Currently, about 82% of the work necessary for ensuring the reliable operation of energy facilities during the winter period has been completed,” the inspection reports.
Monitoring and Inspection Results
During the analysis, specialists from the State Energy Supervision took into account the level of implementation of recommendations provided after this year’s monitoring of electricity supply security, particularly regarding the timely conduct of scheduled equipment repairs.
As part of the relevant commissions, inspection representatives checked the readiness status of 27 distribution system operators. As a result of these inspections, nearly 3,500 comments were identified regarding the technical condition of the electric grid and the organization of its operation. The management of the distribution system operators has already received recommendations for addressing the deficiencies, and according to the latest data, operators have eliminated 64% of them.
The State Energy Supervision continues to monitor the dynamics of implementing recommendations and planned measures to ensure the timely preparation of Ukraine’s energy infrastructure for the autumn-winter period.